Key takeaways
- Sheets = surface area × (1 + waste) ÷ sheet area, rounded up.
- Screw and compound amounts come from an older USG table, so treat them as estimates.
- The IRC limits wall screws to 12 inches where studs are 24 inches apart, which is closer than USG's older figure.
Enter your room's size, measured openings and sheet size. The tool gives sheets to buy, plus fasteners and finishing materials.
How the calculator works
- Area: 2 × (length + width) × height − openings, plus the ceiling if included
- Sheets: area × (1 + waste %) ÷ sheet area, rounded up
- Materials: area × USG's rate per square foot
| Material | Per 1,000 sq ft of panel (USG) |
|---|---|
| Type W screws | 2.7 lb |
| Joint tape | 370 ft |
| All-purpose ready-mixed compound | 138 lb |
| Lightweight ready-mixed compound | 9.4 gal |
These come from USG's installation and finishing guide, an older undated copy, so check your product's current data. We default to 10% waste, a rule of thumb from calculator sites rather than a USG figure.
Worked example
A 12 × 12 foot room with 8-foot walls, a 21-square-foot door and the ceiling, using 4 × 8 sheets and 10% waste:
- Walls: 384 − 21 = 363 square feet
- With ceiling: 363 + 144 = 507 square feet
- Sheets: 507 × 1.10 ÷ 32 = 17.4, so 18 sheets
- Screws: about 1.4 lb. Tape: about 188 feet. Compound: about 70 lb, or 4.8 gallons of lightweight
How sheet size changes your count
For the same 507 square feet with 10% waste:
| Sheet | Coverage | Sheets |
|---|---|---|
| 4 × 8 ft | 32 sq ft | 18 |
| 4 × 10 ft | 40 sq ft | 14 |
| 4 × 12 ft | 48 sq ft | 12 |
Longer sheets can mean fewer joints, but they're heavier and harder to get up stairs and around corners.
Fastener spacing: where sources disagree
USG's older guide lists wall screws at 16 inches. 2021 IRC Table R702.3.5 limits them to 12 inches where wall framing is 24 inches on center. If your studs are 24 inches apart, use the code's figure, as your screw count will be higher. Check the table and your local code for your thickness and framing.
USG also says to keep screws at least 3/8 inch from panel ends and edges.
Older walls and ceilings
Stop before you cut, sand or demolish old surfaces. CPSC says many building products contained asbestos until the 1970s, including textured paint and patching compounds. Old paint can also contain lead. Get advice before you disturb them.
Once your drywall's up, use the paint calculator.
Frequently asked questions
How many sheets of drywall do I need for a 12 × 12 room?
With 8-foot walls, a door and the ceiling, about 18 sheets of 4 × 8 at 10% waste.
How much joint compound do I need?
USG's table gives about 138 lb of all-purpose, or 9.4 gallons of lightweight, per 1,000 square feet.
What thickness should I use?
Requirements depend on framing spacing, location and fire rules. Check your local code and the panel maker.
Sources
We use primary sources where we can: building codes, federal rules and manufacturer documents. Read our editorial standards.
- USG: Sheetrock installation and finishing guide (older copy)
- 2021 International Residential Code, Chapter 7, Table R702.3.5
- CPSC: Asbestos in the home