Concrete Steps Calculator: Yards and Bags

Work out how much concrete solid steps need, with an optional top landing, in cubic yards and bags, plus the code's step figures and what to check first.

Key takeaways

  • Each solid step is as deep as all the treads in front of it, so volume climbs quickly with height.
  • A top landing often uses more concrete than the steps.
  • This gives volume only, so footing and reinforcement questions go to your building department.

Enter the width, number of steps, and each step's rise and tread. Add a top landing if the steps end at a door. The tool assumes solid steps down to the bottom step's base.

  • Concrete needed0.53 cubic yards14.4 cubic feet, including your extra allowance
  • 80 lb bags25 bagsAbout 2,000 lb to move and mix
  • 60 lb bags33 bags
  • 40 lb bags49 bags

Nothing you enter leaves your browser. Gives volume for solid steps. Footings, reinforcement and attachment come from your local code or an engineer.

Show the math with your numbers
  1. Steps: 4 × 7.5 × 11 × (3 × 4 ÷ 2) ÷ 144
  2. Total: 13.75 cu ft, or 14.44 with extra
  3. Yards: 14.44 ÷ 27 = 0.53
What if: number of steps
Number of stepsConcrete needed
10.09 cubic yards
20.27 cubic yards
3 (yours)0.53 cubic yards
40.89 cubic yards
51.34 cubic yards
61.87 cubic yards

How the calculator works

  • Steps: width × rise × tread × (steps × (steps + 1) ÷ 2)
  • Landing: width × landing depth × total rise
  • Yards: total cubic feet ÷ 27

The middle part counts how the steps stack. With three steps, the bottom row holds 3 treads of concrete, the next 2, and the top 1, which makes 6 in all.

Worked example

Three steps, 4 feet wide, with a 7 1/2-inch rise and 11-inch tread, and 5% extra:

  • 4 × 7.5 × 11 × 6 ÷ 144 = 13.75 cubic feet
  • With extra: 14.4 cubic feet, or about 0.53 cubic yards
  • 25 bags of 80 lb

The landing changes everything

Same steps, adding a 36-inch deep landing at the top:

Part Cubic feet
Three steps 13.75
36 in landing, 4 ft wide, 22.5 in high 22.50
Total 36.25

So the landing is more than the steps themselves. Check the landing requirement before you plan the pour. The 2021 IRC calls for a landing at the top and bottom of each stairway, with exceptions, and these changed in the 2024 edition.

Step sizes

The 2021 International Residential Code's figures for stairs serving a building are a riser of at most 7 3/4 inches and a tread of at least 10 inches. To work out how many steps you need, use the stair calculator. Exterior landscape steps not serving a building, porch or deck can be excepted, so ask your building department.

Before you pour

  • Base: ask what footing your steps need. Frost and soil can move steps that aren't supported properly, and the IRC's frost rules are in Section R403.
  • Connection: ask how the steps should relate to the house, because a rigid connection can cause trouble if either one moves.
  • Reinforcement: this comes from your local rules or an engineer.
  • Handrail: the 2021 IRC calls for one on flights with four or more risers.
  • Digging: contact 811 a few business days ahead.

Frequently asked questions

How much concrete for 3 steps?

For steps 4 feet wide, with a 7 1/2-inch rise and 11-inch tread, about 13.75 cubic feet before any allowance.

How many bags for concrete steps?

The same 3 steps take 23 bags of 80 lb with no allowance, or 25 with 5% extra. Use the calculator for your size.

Can I reduce the concrete with fill?

Builders sometimes do, but it changes the structure and the calculation. Ask your building department or a contractor.